13 jobs · open one for files and quote detail
Live
| Site | Area | Stage | Hand-off | Contractors | Working | Quote total |
|---|---|---|---|---|---|---|
| AWS DAL100 TI (same job as "AWS DFW100 Bldg 1 & 3" — assumed) Amazon Web Services SCOPE CHANGE · 11→12-set SCOPE CHANGE · 11→12-set redesign (mail). Morley chose 2M 10/15 (Andrew Mayer). Matt 10/16: Jason handling. Nick 10/17: factory revising/revised (Jason handling); next PO from CED onto factory. | Dallas | Quoted — awaiting PO · SCOPE CHANGE | Morley Moss · Jason Barrett | Unclaimed | SCOPE CHANGE · 11→12-set redesign — Q260969 issued 10/16/26 to Morley (CED Dallas only; amount in PDF) | |
| QTS DFW2 - DC5 alt DC6 / DC7 / DC8 QTS DC7 tray quoted to Loenbro 10/6 (CF181-2134289.1), later resubmitted. | Wilmer | Pending | Loenbro Prism Walker | Unclaimed | $4,994,300 (Walker) | |
| Nexus HB2 Nexus No cable bus BOM yet. HB3 busway closed 9/30. | Hubbard | Pending | — | Unclaimed | — | |
| Project Haskell / Haskell Data Center Haskell (site unstated) IFC cable bus BOM 9/23. Jason running it. Site still unstated. | DFW | BOM | — | Unclaimed | Not in email text | |
| CEC Facilities - NDA project (cable bus + 2000A busway) Undisclosed (NDA) Second cable bus RFQ 9/11/26. Name stays under NDA. | Not disclosed | NDA | CEC Facilities | Unclaimed | — | |
| DLR DFW45 Suites (Digital Realty) Digital Realty Quote sent 9/4/26. Amount lives in the PDF. | DFW | Quoted | DP Electric | Unclaimed | Quote sent 9/4/26 (amount is in the PDF, not the email text) | |
| Powerhouse - AWB Powerhouse RFQ 8/25/26. Cable bus vs tray still open. | Midlothian | RFQ | Powerhouse | Unclaimed | — | |
| DLR DFW37 - Suites 100/200, 105/205, 110/210 Digital Realty Pending opportunity for 2026/27. Morley late on BOMs. | DFW | Pending | CEC Humphrey Morley Moss Walker | Unclaimed | $455K-$1.19M per suite; latest S110 $906,400 and S210 $1,189,800 (Walker, 1/23/26) | |
| DLR Garland DH03 Digital Realty No start date. CED Dallas Salesforce close was 10/26/26. | Garland | Pending | CEC Facilities | Unclaimed | $1,689,317.50 (quoted 2/12/26) | |
| CyrusOne Bldg 21E - Jack/Wise CyrusOne Bid invite 8/19, due 8/25/26. No quote correspondence found. | Jack / Wise County | Bid | Walker Engineering | Unclaimed | — | |
| Walker Engineering - NDA cable bus invites Undisclosed (NDA) Invites through 7/1. May overlap DLR or QTS. | Not disclosed | NDA | Walker Engineering | Unclaimed | — | |
| Edged DFW02 Edged RFQ 5/26. No cable bus quote found. | Irving | RFQ | DP Electric | Unclaimed | — | |
| Equinix DA11-4 Equinix Won. Invoiced 9/10/25 through 3/2/26. | Dallas | Won | — | Unclaimed | $513,124 invoiced |