Projects / Dallas
Amazon Web Services · Dallas
SCOPE CHANGE · 11→12-set
SCOPE CHANGE · 11→12-set redesign (mail). Morley chose 2M 10/15 (Andrew Mayer). Matt 10/16: Jason handling. Nick 10/17: factory revising/revised (Jason handling); next PO from CED onto factory.
Next: Jason Barrett (jason@2meli.com) handling — get PO from CED Dallas onto factory for scheduling/design; keep Matt Cyrus and Scott Thomas looped. March '27 delivery supportable.
Responsible: Jason Barrett (2M) · jason@2meli.com
One tap to update. Drag the card on the board. Undo is available on the card.
2M only
SCOPE CHANGE · 11→12-set redesign — Q260969 issued 10/16/26 to Morley (CED Dallas only; amount in PDF)
Members never receive this field.
1 file
Download everything for this job here. Quotes and pricing files are 2M only; other files default to the desk or your company plus 2M.
DAL100-spec-section.pdf
Spec · v1 · 84 B · All desk members · 2M
Read from uploaded plans and specs. Drafts stay here until a person sends them.
No Division 26 or 27 reading yet.
Spec, distributor quote, and manufacturer support can all be claimed. The same role twice is a conflict, not a block. Claims last 30 days.
Strength comes from how often and how recently someone emailed. Message text stays private.
No relationship metadata on this job yet.
Hold-to-talk from the phone, or upload a recording. Transcription uses the hook when it is configured.
In Spec is only when 2M is working with an engineering firm. Otherwise use Quote / Negotiation, then Handed Off or Quoted.
Who carries each contractor — a 2M, Legrand, or Bell & McCoy person. Nobody gets two numbers from Legrand.
SCOPE CHANGE · 11→12-set redesign (mail). Morley chose 2M 10/15 (Andrew Mayer). Matt 10/16: Jason handling. Nick 10/17: factory revising/revised (Jason handling); next PO from CED onto factory.
Oct 17, 2026 · Next: Jason Barrett (jason@2meli.com) handling — get PO from CED Dallas onto factory for scheduling/design; keep Matt Cyrus and Scott Thomas looped. March '27 delivery supportable.
Direct / Morley Moss via 2M; distribution CED Dallas
Nick 10/17: next is PO from CED
Nick to Matt: factory revising quote or already did (Jason handling). Next step: PO from CED onto factory for scheduling and design; keep Legrand NTX copied.
Oct 17, 2026 · msg:6187043
SCOPE CHANGE · 11→12-set redesign (mail-grounded)
From Oct 7–17 mail: 11→12-set redesign (GEN-to-USB; XFMR 12-set add alt pending GC). Morley chose 2M 10/15; Jason handling; next PO from CED onto factory. Dollars remain in Q260969 PDF.
Oct 17, 2026 · note:scope-change-2026-10-23
Jason quoted Q260969 to Morley 10/16
Q260969 + cross-section sent to Morley; valid for CED Dallas only (Jeff Kerr copied); March '27 delivery supportable. Factory (Swar) had issued distributor-net quote earlier same day.
Oct 16, 2026 · msg:6150682
Morley chose 2M to price 10/15
Andrew Mayer: Morley upper management decided to move forward with 2M Electrical for Power Busway pricing; resume pricing and submittals. Jason: 10-4, on it.
Oct 15, 2026 · msg:6090490
Morley IFP RFP reissued 10/14 (Andrew Mayer)
AWS DAL100 TI IFP cable bus RFP + submittals. Under contract; ROJ 3/15/2027; 4000A 480V; 56 runs. GEN-to-USB to 12-set; ask add alternate XFMR-to-USB 12-set pending GC.
Oct 14, 2026 · msg:6038413
Jason mail: Morley RFP 10/7; Matt Cyrus 10/7-10/8
Morley paused pricing 10/7 pending 12-set redesign. Jason no-quoted 10/8 and voided the PBW request; Legrand (Matt Cyrus) to quote Morley direct. ROJ est. 3/15/2027
Oct 8, 2026 · seed:aws-dal100-ti
No comments yet. Leave the next step where the other firms can see it.
Mail-grounded refresh: SCOPE CHANGE 11→12-set redesign visible; Jason Barrett (jason@2meli.com) handling; next PO from CED onto factory. Chat claims of order doubled / Jason receives PO not found in mail.
Refreshed from mail after 10/8: Morley reissued IFP RFP 10/14, chose 2M 10/15, Jason quoted Q260969 10/16 (CED Dallas), Nick 10/17 awaiting PO from CED. Status Handed Off → Quoted.
Imported from the 12 Oct 2026 PBW list, DFW to Waco.